IOC-MIPS_230a |
|
|
10470C |
|
|
|
|
|
Title: |
|
Effect of Bias Levels and Integration Times on Sensitivity |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Objective: |
|
To optimize instrument sensitivity. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Description: |
|
A standard AOT will be executed at various bias levels and integration times to find the |
|
|
|
|
|
|
|
|
optimum settings for in-orbit operation given the realities of cosmic-ray effects. |
|
|
|
|
|
|
|
|
This is not intended to determine the ultimate sensitivity of the instrument, but it should |
|
|
|
|
|
|
|
|
allow us to select a standard set of bias levels and integration times for routine observing. |
|
|
|
|
|
|
|
|
We should pick a standard star to observe with each array, which means that we'll have to |
|
|
|
|
|
|
|
|
optimize each array separately. With three arrays and perhaps 4 different bias |
|
|
|
|
|
|
|
|
levels, that implies 12 photometry AOTs. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Place in Schedule: |
|
The telescope must be cold enough to measure standard stars at 70 and 160 microns. |
|
|
|
|
|
|
|
|
The photometry AOT must be checked out and working properly. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Required Conditions: |
|
The pointing accuracy and stability have to be enough to measure a standard star in a |
|
|
|
|
|
|
|
|
short integration time - pointing of 10", stability of 0.6" in 3 seconds. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Resources: |
|
|
|
|
|
|
|
|
|
duration (best estimate) |
|
|
|
85 minutes |
|
|
|
|
real time downlink (Y / N) |
|
|
|
n |
|
|
|
|
special post event actions (Y / N) |
|
|
|
data must be analyzed |
|
|
|
|
|
|
|
|
|
|
|
|
Outcome: |
|
|
|
|
|
|
|
|
|
description |
|
|
|
|
generates a series of SUR exposures |
|
|
|
can proceed in parallel with other activity |
|
|
|
|
no |
|
|
|
must outcome be confirmed before next event / test /activity |
|
|
|
|
no |
|
|
|
method of confirmation (sensor TLM, data analysis, etc.) |
|
|
|
|
analysis |
|
|
|
estimate of data turn around if required for confirmation |
|
|
|
|
|
|
|
|
number of DCEs |
|
|
|
|
144 |
|
|
|
|
|
|
|
|
|
|
|
Unique or included in planned uplink or downlink/analysis tool |
|
|
|
|
should use planned AOTs |
|
|
|
|
|
|
|
|
|
|
|
|
Contingency Plan: |
|
|
|
|
|
|
|
|
"What if..." |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
IOC Critical |
|
|
|
|
Y |
|
|
|
|
|
|
|
|
|
|
|
|
References: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Template last updated: |
|
|
|
|
11-Sep-95 |
|
|
|
|
|
|
|
|
C. W. Engelbracht |
|
|
|
|
|
|
|
|
|
|
|
|