MIPS_265a Confusion Level


IOC-MIPS_265a     10720C          
Title:   MIPS Scan to Determine Confusion Limits            
                 
Objective:   Deep observations at 70 and 160 microns to estimate the MIPS confusion            
    limits at three galactic latitudes (low background, high, and intermediate).            
                 
Description:   Acquire normal scan observations at 70 and 160 microns of three 5 arcmin X 0.5 degree fields            
    at, or near the galactic pole, the equator, and an intermediate position.            
                 
    Can be the same as:   Verify pipeline -- Scan        
                 
    Three identical AORs executed at three different pointings:            
      Slow scan rate, 0.5 degree leg length (full coverage), 4 up and back scan legs with minimum offset step          
                 
Place in Schedule:   After CTA/instrument cool down and all other instrument testing is complete.            
    For 160 um performance, the backgrd radiance must be less than 5.2E-13 W/cm2/sr (< 6 K).            
    Can be concurrent with other AOT/instrument tests.            
                 
Required Conditions:   CTA and instrument at nominal operating temperature for the 160 um band (< 6 K).            
    PCS performance needs to be nominal in pointing, offsetting, and scan stability.            
                 
Resources:                
  duration (best estimate)         2 hours    
  real time downlink (Y / N)         No    
  special post event actions (Y / N)         No    
                 
Outcome:                
  description         Fully calibrated MIPS scan data products in three bands.    
  can proceed in parallel with other activity         No - dedicated observing    
  must outcome be confirmed before next event / test /activity         No    
  method of confirmation (sensor TLM, data analysis, etc.)         Data analysis    
  estimate of data turn around if required for confirmation         7 days    
                 
Unique or included in planned uplink or downlink/analysis tool           Standard pipeline system and standard data analysis tools required.    
            MIPS scan AOT required for uplink.    
                 
Contingency Plan:                
"What if..."         Revisit pipeline and/or AOT design depending on the nature of a failure.      
                 
IOC Critical         No      
                 
References:                
                 
Template last updated:           1-Sep-99    
Template written by:           William B. Latter    
                 
                 
                 


Last Updated on 10/7/99
By Marcia Rieke