IOC-MIPS_290a |
|
|
18870C,10760C,10770C,10530C |
|
|
|
|
|
Title: |
|
MIPS Scan Map of the HH 7-11 Region |
|
|
|
|
|
|
|
|
Note: |
This region has very bright IR sources -- this test can investigate how much of an impact there will be in an AOR. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Objective: |
|
Verify scientific validity of MIPS Scan pipeline products and ERO |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Description: |
|
Acquire normal scan map observations of the HH 7-11 region over a field 1.0 degree square field. |
|
|
|
|
|
|
|
|
|
Fast scan rate, 60 arcminute square field, 5 arcmin leg offsets, 4 cycles |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Can be the same as: |
|
Evaluate fully supported AOTs (MIPS Scan) |
|
|
|
|
|
|
|
|
ERO: Press release observation |
|
|
|
|
|
|
|
|
|
|
|
|
|
Place in Schedule: |
|
After apertrue door open |
|
|
|
|
|
|
|
|
After CTA/instrument cool down and all other instrument testing is complete. |
|
|
|
|
|
|
|
|
For 160um, the backgrd radiance must be less than 5.4E-13 W/cm2/sr (< 6 - 7 K). |
|
|
|
|
|
|
|
|
After Scan AOT functionality testing is complete. |
|
|
|
|
|
|
|
|
Can be concurrent with other AOT/instrument tests. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Required Conditions: |
|
CTA and instrument at nominal operating temperature for 160 micron band (mirror at 6 K). |
|
|
|
|
|
|
|
|
PCS performance: 10 arcsec pointing and nominal offsetting and scan stability |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Resources: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
duration (best estimate) |
|
|
|
|
3.0 hrs |
|
|
|
real time downlink (Y / N) |
|
|
|
|
No |
|
|
|
special post event actions (Y / N) |
|
|
|
|
No |
|
|
|
|
|
|
|
|
|
|
|
Outcome: |
|
|
|
|
|
|
|
|
|
description |
|
|
|
|
Fully calibrated MIPS scan map data products in three bands. |
|
|
|
can proceed in parallel with other activity |
|
|
|
|
No - dedicated observing |
|
|
|
must outcome be confirmed before next event / test /activity |
|
|
|
|
No |
|
|
|
method of confirmation (sensor TLM, data analysis, etc.) |
|
|
|
|
Data analysis |
|
|
|
estimate of data turn around if required for confirmation |
|
|
|
|
48 hrs |
|
|
|
|
|
|
|
|
|
|
|
Unique or included in planned uplink or downlink/analysis tool |
|
|
|
|
|
Standard pipeline system and standard data analysis tools required. |
|
|
|
|
|
|
|
|
MIPS Scan AOT required for uplink. |
|
|
|
|
|
|
|
|
|
|
|
Contingency Plan: |
|
|
|
|
|
Revisit pipeline and/or AOT design depending on the nature of failure. |
|
|
"What if..." |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
IOC Critical |
|
|
|
|
|
No |
|
|
|
|
|
|
|
|
|
|
|
References: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Template last updated: |
|
|
|
|
|
2-Sep-99 |
|
|
Template written by: |
|
|
|
|
|
William B. Latter |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|