MIPS IOC Strategy
IOC Criticality Determination
- What must be done before operations can begin?
- What needs to be done for proposers?
- Critical = basic operations. Derivation of operating parameters, e.g.
- sensitivity/saturation
- optimum bias voltage
- anneal frequency
- stimulator brightness
- AOT commissioning
- Critical = key functionality tests
- Test A must come before IOC critical test B but after test C
- Not IOC critical = detailed characterization, e.g.
- Ultimate calibration
- Geometric characterization of the arrays
- SED slit mapping