MIPS IOC Task List Summary
Sixty-two to ? seventy MIPS IOC tasks have been identified and placed onto the provisional IOC timeline.
Total MIPS estimated IOC time is:
- 6 x 24 hour days IOC critical and non-critical
- 5 days IOC critical only
- 5.33 days IOC critical and non-critical requiring CTA T < 9 K
- 4.24 days IOC critical CTA T < 9 K
-
No time has been allotted for failed tests or retests
- argues for break-out of 24 mm data acquisition for earlier execution of critical functionality testing
- more total time needed
- slightly more bias toward under-subscribed “warm” period
- fewer test failures during critical and overburdened full cold testing period