MIPS IOC Planning To Be Done List (2)
Determine and correct for the “human factor” in the provisional timeline.
- What is a realistic maximum SI campaign length for success?
- The provisional timeline does not account for the limited MIPS/SSC workforce who must
- process, analyze, and understand large quantities of data in a short period of time
- prepare following tasks in real time that need to include results of previous tasks
- understand failures and prepare revised tasks to replace failed ones
Re-examine IOC critical flagging.
Does the First Look Survey have an unanticipated impact on IOC strategy?