| IOC-MIOS_025a | 10210C | ||||||
| Title: | Scan Mirror Operational Test | ||||||
| Objective: | This is a test to ensure that the scan mirror and its position readout are functional. | ||||||
| Description: | We issue a series of CESCANPOS commands and monitor the telemetry | ||||||
| and compare the results to ground testing | |||||||
| Place in Schedule: | during initial electronics checkout | ||||||
| Required Conditions: | no PCS capabilities are required - CE must be working | ||||||
| Resources: | |||||||
| duration (best estimate) | 1 minute | ||||||
| real time downlink (Y / N) | n | ||||||
| special post event actions (Y / N) | none | ||||||
| Outcome: | |||||||
| description | scan mirror position telemetry | ||||||
| can proceed in parallel with other activity | yes | ||||||
| must outcome be confirmed before next event / test /activity | we can't use the CSMM until we confirm it's working | ||||||
| method of confirmation (sensor TLM, data analysis, etc.) | telemetry analysis | ||||||
| estimate of data turn around if required for confirmation | |||||||
| number of DCEs | 0 | ||||||
| Unique or included in planned uplink or downlink/analysis tool | unique | ||||||
| Contingency Plan: | |||||||
| "What if..." | |||||||
| IOC Critical | Y | ||||||
| References: | |||||||
| Template last updated: | 11-Sep-95 | ||||||
| C.W. Engelbracht | |||||||