Sequencer Site SIRTF IOC Activity c. 2002

CAID: MIPS-010 Title: Start-up Activities, Si, Campaign A
 
System: MIPS Principal: dmkelly Deputy: cengelbracht
Objective:  
Transition MIPS up to MIPS_Observe in 
preparation
for
            MIPS-015, the initial power-on
aliveness test.
 
Description:
1) Turn on power to the combined electronics
   2) Transition from OFF to MIPS_OBSERVE
 
Day:   0 Suggested Order:   A010
 
Must be preceded by these activities (list by CAID):  
 
Place in Schedule:   At the start of campaign A
 
Priority:   Critical


Conditions

Maximum telescope temperature: 300 K
 
Minimum telescope temperature: 5.5 K
 
Should activity be repeated if focus changes?   No     Repeat if focus changes by 0 mm
 
Maximum absolute pointing uncertainty: 3600 arcsec (1 sigma radial)
 
Maximum precision offset uncertainty: 3600 arcsec  (1 sigma radial)
 
Observatory configuration: standard
 
Go/No Go criteria:


Resources

Duration:   10 minutes
 
Real time downlink:   No   

Data Volume (uncompressed): 0 Mbits
 
List Blocks, AORs, SERs, IERs, or unique sequences required (uplink): Power-on and state transition blocks
 
List Analysis tools required (downlink):  

Outcome


Estimate of data turn around:   0 hours
 
Description:
 
Can proceed in parallel with other activity: No
 
Must outcome be confirmed before next activity: No
 
Method of Confirmation:   Visual inspection of telemetry
 
 
Success criteria: The electronics reaches the MIPS_Observe state with no errors
 
Contingency plan:  None
 
 

Comments

 
References:  
 
Additional Comments:
 
This activity last updated: 5/20/2002 10:15:14 AM