CAID: MIPS-010 | Title: Start-up Activities, Si, Campaign A | |
System: MIPS | Principal: dmkelly | Deputy: cengelbracht |
Objective: | Transition MIPS up to MIPS_Observe in preparation for MIPS-015, the initial power-on aliveness test. |
Description: | 1) Turn on power to the combined electronics 2) Transition from OFF to MIPS_OBSERVE |
Day: 0 | Suggested Order: A010 | ||
Must be preceded by these activities (list by CAID): | |||
Place in Schedule: At the start of campaign A | |||
Priority: Critical | |||
Conditions | |||
Maximum telescope temperature: | 300 K | ||
Minimum telescope temperature: | 5.5 K | ||
Should activity be repeated if focus changes? | No Repeat if focus changes by 0 mm | ||
Maximum absolute pointing uncertainty: | 3600 arcsec (1 sigma radial) | ||
Maximum precision offset uncertainty: | 3600 arcsec (1 sigma radial) | ||
Observatory configuration: | standard | ||
Go/No Go criteria: | |||
Duration: 10 minutes
| Real time downlink:
 
No | |
Data Volume (uncompressed): 0 Mbits | |||
List Blocks, AORs, SERs, IERs, or unique sequences required (uplink): Power-on and state transition blocks | |||
List Analysis tools required (downlink): | |||
Estimate of data turn around: 0 hours | |||
Description: | |||
Can proceed in parallel with other activity: No | |||
Must outcome be confirmed before next activity: No | |||
Method of Confirmation: Visual inspection of telemetry | |||
Success criteria: The electronics reaches the MIPS_Observe state with no errors | |||
Contingency plan: None | |||
Comments | |||
References: | |||
Additional Comments:
| |||
This activity last updated: 5/20/2002 10:15:14 AM |