CAID: MIPS-095 | Title: Shut-down activities, Campaign A, Part II | |
System: MIPS | Principal: dmkelly | Deputy: cengelbracht |
Objective: | Power off MIPS at the end of MIPS Campaign A |
Description: | 1) Transition from MIPS_OPERATE to OFF 2) Turn off power to the combined electronics |
Day: 0 | Suggested Order: A905 | ||
Must be preceded by these activities (list by CAID): MIPS-015, MIPS-090, MIPS-092 | |||
Place in Schedule: At the end of MIPS campaign A, 12-24 hours after the completion of MIPS-090 | |||
Priority: Necessary | |||
Conditions | |||
Maximum telescope temperature: | 300 K | ||
Minimum telescope temperature: | 5.5 K | ||
Should activity be repeated if focus changes? | No Repeat if focus changes by 0 mm | ||
Maximum absolute pointing uncertainty: | 3600 arcsec (1 sigma radial) | ||
Maximum precision offset uncertainty: | 3600 arcsec (1 sigma radial) | ||
Observatory configuration: | standard | ||
Go/No Go criteria: | |||
Duration: 5 minutes
| Real time downlink:
 
No | |
Data Volume (uncompressed): 0 Mbits | |||
List Blocks, AORs, SERs, IERs, or unique sequences required (uplink): State transition and power-off blocks | |||
List Analysis tools required (downlink): | |||
Estimate of data turn around: 0 hours | |||
Description: | |||
Can proceed in parallel with other activity: No | |||
Must outcome be confirmed before next activity: No | |||
Method of Confirmation: Visual inspection of telemetry | |||
Success criteria: The electronics are transitioned down to BOOT and then powered off without errors. | |||
Contingency plan: None | |||
Comments | |||
References: | |||
Additional Comments:
MIPS places no restrictions on parallel activities during the 12-24h between the completion of MIPS-090 and the running of MIPS-095. | |||
This activity last updated: 4/9/2002 12:02:53 PM |