Sequencer Site SIRTF IOC Activity c. 2002

CAID: MIPS-300 Title: SED Skeleton AOT Validation
 
System: MIPS Principal: psmith Deputy: 
Objective:  
Explore MIPS SED AOT parameter space
 
Description:
Execute MIPS SED AOT for a sensible range 
of parameters with a bright point source 
(~1 Jy flux standard at 70 microns) as the 
target.  Valuable diagnostics on SED-mode 
performance and calibration can be gained if 
the chosen target is a flux calibtation star.

The SED AOT front end allows two integration 
times (3 and 10 seconds) as well as 4 different 
chop configurations (1, 2, 3, and -1 arcminutes). 
For a skeleton AOT, I would like to test both 
integration times, all chop configurations, and 
multiple cycles in one of those chop 
configurations and in both integration times 
(to look for any timing problems).

Because the useful SED range is little more 
than 3 arcminutes, the on-source position 
can't be in the same place for both positive 
and negative chops (i.e., to get all the way 
from -1 arcminutes to +3, we'd need a 
4-arcminute range). I have chosen to make 
the on-source position the same for all the 
positive chops (at 3100 SCANABS counts) and 
to move the on-source position for the -1 
arcminute chop to the sky position for the 
+1 arcminute chop (at 3204 SCANABS counts).  
Thus, the S/C will have to maintain two 
different locations for SED mode:  1 for 
positive chops and 1 for negative chops.

Tests to run:

AT ON-SOURCE POSITION 1:
1) chop=1, itime=3, cycles=1 (mips_sed_itime3_chop1_cycle1.exp)
2) chop=1, itime=10, cycles=1 (mips_sed_itime10_chop1_cycle1.exp)
3) chop=1, itime=3, cycles=7 (mips_sed_itime3_chop1_cycle7.exp)
4) chop=1, itime=10, cycles=7 (mips_sed_itime10_chop1_cycle7.exp)
5) chop=2, itime=3, cycles=1 (mips_sed_itime3_chop2_cycle1.exp)
6) chop=3, itime=3, cycles=1 (mips_sed_itime3_chop3_cycle1.exp)

AT ON-SOURCE POSITION 2:
7) chop=-1, itime=3, cycles=1 (mips_sed_itime3_chop-1_cycle1.exp)
 
Day:   50.882638888892 Suggested Order:   K100
 
Must be preceded by these activities (list by CAID):   MIPS-139
 
Place in Schedule:   After aperture door open. After CTA/instrument cool down: For 70um, the backgrd radiance must be less than 1.0E-12 W/cm2/sr (< 12 K). Location of MIPS apertures must be completed. Basic instrument commanding and functionality must have been confirmed.
 
Priority:   Critical


Conditions

Maximum telescope temperature: 12 K
 
Minimum telescope temperature: 5.5 K
 
Should activity be repeated if focus changes?   Yes     Repeat if focus changes by 0 mm
 
Maximum absolute pointing uncertainty: 5 arcsec (1 sigma radial)
 
Maximum precision offset uncertainty: 1 arcsec  (1 sigma radial)
 
Observatory configuration: standard
 
Go/No Go criteria: CSMM and CE nominal.


Resources

Duration:   42 minutes
 
Real time downlink:   No   

Data Volume (uncompressed): 394 Mbits
 
List Blocks, AORs, SERs, IERs, or unique sequences required (uplink): MIPS SED skeleton AOT required
 
List Analysis tools required (downlink):   Standard pipeline if available for skeleton AOT and data analysis tools.

Outcome


Estimate of data turn around:   48 hours
 
Description: 1) Confirm that scan mirror motions and array operations were as expected. 2) Confirm that sensitivity limits reached were as expected.
 
Can proceed in parallel with other activity: No
 
Must outcome be confirmed before next activity: No
 
Method of Confirmation:   Data and telemetry analysis
 
 
Success criteria: Scan mirror and array operation as expected, sensitivity limits as expected.
 
Contingency plan:  Revisit uplink sequence/command expansion, or AOT design.
 
 

Comments

 
References:  
 
Additional Comments:
It would be useful if the target observed is a 70um flux calibrator. PSS 11/19/01
 
This activity last updated: 10/22/2002 8:00:29 PM