CAID: MIPS-320 Title: 24 um Ph/SR AOT Validation - preliminary
 
System: MIPS Principal: dlp Deputy: cengelbracht
Objective:  
Confirm that 24 um small field photometry works as
expected
 
Description:
Execute MIPS Phot/SR AOT for a few selectable
parameters.	

Tune IPP files as needed
		
Several AORs will be constructed that will have:
1) one small field  24um AOR for each 
available exposure time (3s, 10s, 30s)

2) 3 cycles of small field 24um photometry (3s
only)
 
Day:   31.871527777781 Suggested Order:   D300
 
Must be preceded by these activities (list by CAID):   MIPS-100, MIPS-110
 
Place in Schedule:   After aperture door open, After CTA/instrument cool down: For 24um, the backgrd radiance must be less than 1.0E-11 W/cm2/sr (< 30K). Before final operational parameters are set and instrument tuning complete.
 
Priority:   Critical


Conditions

Maximum telescope temperature: 33 K
 
Minimum telescope temperature: 5.5 K
 
Should activity be repeated if focus changes?   No     Repeat if focus changes by 0 mm
 
Maximum absolute pointing uncertainty: 10 arcsec (1 sigma radial)
 
Maximum precision offset uncertainty: 1.4 arcsec  (1 sigma radial)
 
Observatory configuration: standard
 
Go/No Go criteria: CE, MIPS, CSMM all working as expected; solar activity normal


Resources

Duration:   30 minutes
 
Real time downlink:   No   

Data Volume (uncompressed): 67 Mbits
 
List Blocks, AORs, SERs, IERs, or unique sequences required (uplink): Standard pipeline and data analysis tools. MIPS Phot/SR AOT required
 
List Analysis tools required (downlink):   MIPS pipeline; image analysis tools; telemetry analysis tools

Outcome


Estimate of data turn around:   24 hours
 
Description: Perform observations using a few selectable parameters available in the AOT. Verifies basic functionality of the small field photometry 24um AOT.
 
Can proceed in parallel with other activity: No
 
Must outcome be confirmed before next activity: No
 
Method of Confirmation:   Data analysis
 
 
Success criteria: Data downlinked completely; targets unsaturated; motion of CSMM validated as expected; array operation normal
 
Contingency plan:  Revisit uplink sequence/command expansion, or AOT design.
 
 

Comments

 
References:  
 
Additional Comments:
Required Conditions: CTA and instrument at nominal operational temperature. PCS performance: Absolute pointing 10 arcsecs Offsetting nominal. This task must be split into its array components. Make into 3 or 4 tasks.
 
This activity last updated: 4/26/2001 2:28:04 PM