CAID: MIPS-320 | Title: 24 um Ph/SR AOT Validation - preliminary | |
System: MIPS | Principal: dlp | Deputy: cengelbracht |
Objective: | Confirm that 24 um small field photometry works as expected |
Description: | Execute MIPS Phot/SR AOT for a few selectable parameters. Tune IPP files as needed Several AORs will be constructed that will have: 1) one small field 24um AOR for each available exposure time (3s, 10s, 30s) 2) 3 cycles of small field 24um photometry (3s only) |
Day: 31.871527777781 | Suggested Order: D300 | ||
Must be preceded by these activities (list by CAID): MIPS-100, MIPS-110 | |||
Place in Schedule: After aperture door open, After CTA/instrument cool down: For 24um, the backgrd radiance must be less than 1.0E-11 W/cm2/sr (< 30K). Before final operational parameters are set and instrument tuning complete. | |||
Priority: Critical | |||
Conditions | |||
Maximum telescope temperature: | 33 K | ||
Minimum telescope temperature: | 5.5 K | ||
Should activity be repeated if focus changes? | No Repeat if focus changes by 0 mm | ||
Maximum absolute pointing uncertainty: | 10 arcsec (1 sigma radial) | ||
Maximum precision offset uncertainty: | 1.4 arcsec (1 sigma radial) | ||
Observatory configuration: | standard | ||
Go/No Go criteria: | CE, MIPS, CSMM all working as expected; solar activity normal | ||
Duration: 30 minutes
| Real time downlink:
 
No | |
Data Volume (uncompressed): 67 Mbits | |||
List Blocks, AORs, SERs, IERs, or unique sequences required (uplink): Standard pipeline and data analysis tools. MIPS Phot/SR AOT required | |||
List Analysis tools required (downlink): MIPS pipeline; image analysis tools; telemetry analysis tools | |||
Estimate of data turn around: 24 hours | |||
Description: Perform observations using a few selectable parameters available in the AOT. Verifies basic functionality of the small field photometry 24um AOT. | |||
Can proceed in parallel with other activity: No | |||
Must outcome be confirmed before next activity: No | |||
Method of Confirmation: Data analysis | |||
Success criteria: Data downlinked completely; targets unsaturated; motion of CSMM validated as expected; array operation normal | |||
Contingency plan: Revisit uplink sequence/command expansion, or AOT design. | |||
Comments | |||
References: | |||
Additional Comments:
Required Conditions: CTA and instrument at nominal operational temperature. PCS performance: Absolute pointing 10 arcsecs Offsetting nominal. This task must be split into its array components. Make into 3 or 4 tasks. | |||
This activity last updated: 4/26/2001 2:28:04 PM |