CAID: MIPS-323 | Title: 70 um Ph/SR AOT Validation - final | |
System: MIPS | Principal: alberto | Deputy: cengelbracht |
Objective: | Validate the MIPS Photometry AOT (70um) as ready for beginning of science observations. |
Description: | Execute MIPS Phot/SR AOT for a sensible range of selectable parameters. Can be the same as: Select final operational parameters Tune IPP file as needed Several AORs will be constructed that will have : 1) 1 cycle small field/default scale for 3s, 10s 2) 1 cycle small field/fine scale for 3s, 10s 3) 1 cycle large field/default scale for 3s, 10s 4) 1 cycle large field/fine scale for 3s, 10s 5) do 1 - 4 with 3 cycles (3 s only) 6) raster map for 1 3x3 3 s only 7) do 1 for 20 cycles (10s only) |
Day: 65.4375 | Suggested Order: P400 | ||
Must be preceded by these activities (list by CAID): MIPS-322 | |||
Place in Schedule: After preliminary AOT validation, aperture door open, CTA cooldown complete, focus stable, CSMM functioning, commanding checked. This should be the last task to validate the MIPS PH/SR 70um AOT for science observations. | |||
Priority: Necessary | |||
Conditions | |||
Maximum telescope temperature: | 5.5 K | ||
Minimum telescope temperature: | 5.5 K | ||
Should activity be repeated if focus changes? | Yes Repeat if focus changes by 0 mm | ||
Maximum absolute pointing uncertainty: | 3 arcsec (1 sigma radial) | ||
Maximum precision offset uncertainty: | 0.5 arcsec (1 sigma radial) | ||
Observatory configuration: | standard | ||
Go/No Go criteria: | good space weather | ||
Duration: 186 minutes
| Real time downlink:
 
No | |
Data Volume (uncompressed): 695 Mbits | |||
List Blocks, AORs, SERs, IERs, or unique sequences required (uplink): Variety of AORs | |||
List Analysis tools required (downlink): interactive MIPS pipeline; image analysis; telemetry analysis | |||
Estimate of data turn around: 100 hours | |||
Description: Standar Photometry AOTs for 70um (see MIPS Handbook for details). | |||
Can proceed in parallel with other activity: No | |||
Must outcome be confirmed before next activity: No | |||
Method of Confirmation: image and telemetry analysis. Reasonable BCDs should be produced. | |||
Success criteria: 70um MIPS PH/SR judged ready for commissioning. See SSC AOT Validation document by W. Mahoney (2001). | |||
Contingency plan: Photometry is one of the two main observing modes for MIPS. If this mode is not working properly, implement scan mapping observations instead. | |||
Comments | |||
References: | |||
Additional Comments:
| |||
This activity last updated: 10/8/2002 9:52:50 AM |