CAID: MIPS-324 | Title: 160 um First Light & Ph/SR AOT Validation - preliminary | |
System: MIPS | Principal: alberto | Deputy: cengelbracht |
Objective: | Confirm basic functionality of MIPS 160um small field photometry |
Description: | Several AORs will be constructed: 1) 1 cycle 160um small field 3s, 10s 2) 3 cycles 160um small field 3s only |
Day: 48.4847222222306 | Suggested Order: H100 | ||
Must be preceded by these activities (list by CAID): MIPS-102 | |||
Place in Schedule: | |||
Priority: Critical | |||
Conditions | |||
Maximum telescope temperature: | 6.5 K | ||
Minimum telescope temperature: | 5.5 K | ||
Should activity be repeated if focus changes? | No Repeat if focus changes by 0 mm | ||
Maximum absolute pointing uncertainty: | 10 arcsec (1 sigma radial) | ||
Maximum precision offset uncertainty: | 1 arcsec (1 sigma radial) | ||
Observatory configuration: | |||
Go/No Go criteria: | |||
Duration: 18 minutes
| Real time downlink:
 
No | |
Data Volume (uncompressed): 32 Mbits | |||
List Blocks, AORs, SERs, IERs, or unique sequences required (uplink): Several AORs | |||
List Analysis tools required (downlink): image analysis; telemetry analysis | |||
Estimate of data turn around: 24 hours | |||
Description: Use small field photometry for 160um. | |||
Can proceed in parallel with other activity: No | |||
Must outcome be confirmed before next activity: No | |||
Method of Confirmation: Reasonable BCDs products, with miminum artifacts in the images. | |||
Success criteria: The desired number of BCDs is obtained, the quality of the images should be reasonable, based on a target that provides an adequated signal-to-noise. See SSC AOT Validation by W. Mahoney (20 | |||
Contingency plan: Revise AOT logic. Await to full confirmation. | |||
Comments | |||
References: | |||
Additional Comments:
| |||
This activity last updated: 10/8/2002 10:02:06 AM |