Sequencer Site SIRTF IOC Activity c. 2002

CAID: MIPS-325 Title: 160 um Ph/SR AOT Validation - final
 
System: MIPS Principal: alberto Deputy: cengelbracht
Objective:  
Commission the MIPS 160um PH/SR AOT for science
observations
 
Description:
Several AORs will be constructed:

1) 1 cycle small field 3s, 10s
2) 1 cycle large field 3s, 10s
3) 3 cycles each for 1 - 2, 3s only
4) 1 cycle 3x3 raster map, 3s only
5) super-resolution raster map 1x3, 3s only
6) 20 cycles, small field, 3s only
 
Day:   77.2944444444438 Suggested Order:   R400
 
Must be preceded by these activities (list by CAID):   MIPS-324
 
Place in Schedule:   After preliminary AOT validation, aperture door open, CTA cooldown complete, focus stable, CSMM functioning, commanding checked. This should be the last task to validate the MIPS 160um PH/SR AOT for science observations.
 
Priority:   Necessary


Conditions

Maximum telescope temperature: 5.5 K
 
Minimum telescope temperature: 5.5 K
 
Should activity be repeated if focus changes?   Yes     Repeat if focus changes by 0 mm
 
Maximum absolute pointing uncertainty: 3 arcsec (1 sigma radial)
 
Maximum precision offset uncertainty: 0.5 arcsec  (1 sigma radial)
 
Observatory configuration: standard
 
Go/No Go criteria:


Resources

Duration:   120 minutes
 
Real time downlink:   No   

Data Volume (uncompressed): 173 Mbits
 
List Blocks, AORs, SERs, IERs, or unique sequences required (uplink): Several AORs
 
List Analysis tools required (downlink):   interactive MIPS pipeline; image analysis; telemetry analysis

Outcome


Estimate of data turn around:   100 hours
 
Description:
 
Can proceed in parallel with other activity: No
 
Must outcome be confirmed before next activity: No
 
Method of Confirmation:  
 
 
Success criteria:
 
Contingency plan: 
 
 

Comments

 
References:  
 
Additional Comments:
 
This activity last updated: 10/8/2002 9:53:23 AM