CAID: MIPS-325 | Title: 160 um Ph/SR AOT Validation - final | |
System: MIPS | Principal: alberto | Deputy: cengelbracht |
Objective: | Commission the MIPS 160um PH/SR AOT for science observations |
Description: | Several AORs will be constructed: 1) 1 cycle small field 3s, 10s 2) 1 cycle large field 3s, 10s 3) 3 cycles each for 1 - 2, 3s only 4) 1 cycle 3x3 raster map, 3s only 5) super-resolution raster map 1x3, 3s only 6) 20 cycles, small field, 3s only |
Day: 77.2944444444438 | Suggested Order: R400 | ||
Must be preceded by these activities (list by CAID): MIPS-324 | |||
Place in Schedule: After preliminary AOT validation, aperture door open, CTA cooldown complete, focus stable, CSMM functioning, commanding checked. This should be the last task to validate the MIPS 160um PH/SR AOT for science observations. | |||
Priority: Necessary | |||
Conditions | |||
Maximum telescope temperature: | 5.5 K | ||
Minimum telescope temperature: | 5.5 K | ||
Should activity be repeated if focus changes? | Yes Repeat if focus changes by 0 mm | ||
Maximum absolute pointing uncertainty: | 3 arcsec (1 sigma radial) | ||
Maximum precision offset uncertainty: | 0.5 arcsec (1 sigma radial) | ||
Observatory configuration: | standard | ||
Go/No Go criteria: | |||
Duration: 120 minutes
| Real time downlink:
 
No | |
Data Volume (uncompressed): 173 Mbits | |||
List Blocks, AORs, SERs, IERs, or unique sequences required (uplink): Several AORs | |||
List Analysis tools required (downlink): interactive MIPS pipeline; image analysis; telemetry analysis | |||
Estimate of data turn around: 100 hours | |||
Description: | |||
Can proceed in parallel with other activity: No | |||
Must outcome be confirmed before next activity: No | |||
Method of Confirmation: | |||
Success criteria: | |||
Contingency plan: | |||
Comments | |||
References: | |||
Additional Comments:
| |||
This activity last updated: 10/8/2002 9:53:23 AM |