CAID: MIPS-336 | Title: 70 um PSF | |
System: MIPS | Principal: krs | Deputy: dhines |
Objective: | Detailed characterization of the MIPS PSF in both 70 micron coarse and fine scale images. |
Description: | A bright stellar PSF will be moved in a 3x3 grid of positions over the 70 micron array. At each position 3 sec integrations will be taken in an 8x8 grid stepping by 1/4 pixel, in order to sub-sample the PSF. In coarse mode the 3x3 grid will be observed three times, once at the center of the MIPS FOV, and two other times spaced above and below by 1/2 array FOV. In fine mode the 3x3 grid will be observed only once, but using two different targets with red and blue color. |
Day: 81.4944444444482 | Suggested Order: V400 | ||
Must be preceded by these activities (list by CAID): MIPS-306, MIPS-322 | |||
Place in Schedule: | |||
Priority: Desired | |||
Conditions | |||
Maximum telescope temperature: | 12 K | ||
Minimum telescope temperature: | 5.5 K | ||
Should activity be repeated if focus changes? | No Repeat if focus changes by 0 mm | ||
Maximum absolute pointing uncertainty: | 1.5 arcsec (1 sigma radial) | ||
Maximum precision offset uncertainty: | 0.5 arcsec (1 sigma radial) | ||
Observatory configuration: | |||
Go/No Go criteria: | |||
Duration: 447 minutes
| Real time downlink:
 
No | |
Data Volume (uncompressed): 458 Mbits | |||
List Blocks, AORs, SERs, IERs, or unique sequences required (uplink): | |||
List Analysis tools required (downlink): | |||
Estimate of data turn around: 504 hours | |||
Description: | |||
Can proceed in parallel with other activity: No | |||
Must outcome be confirmed before next activity: No | |||
Method of Confirmation: | |||
Success criteria: | |||
Contingency plan: | |||
Comments | |||
References: | |||
Additional Comments:
| |||
This activity last updated: 5/25/2001 10:34:27 AM |