CAID: MIPS-905 | Title: Start-up Activities, Si & Ge | |
System: MIPS | Principal: dmkelly | Deputy: cengelbracht |
Objective: | Prepare the MIPS Si and Ge arrays for science operations by executing a standard set of MIPS turn-on tasks. |
Description: | 1) Turn on power to the combined electronics 2) Transition from OFF to MIPS_OBSERVE 3) Perform thermal anneals on all three arrays 4) Perform a Vrst Optimization on the 70um and 160um arrays 5) Point the telescope to the first desired target 6) Before beginning the next IOC task, wait as necessary until 10 minutes have elapsed since bias was restored to the Ge arrays and 30 minutes has elapsed since the CE power-on |
Day: 42.2673611111168 | Suggested Order: | ||
Must be preceded by these activities (list by CAID): MIPS-015 | |||
Place in Schedule: At the start of each IOC campaign in which Ge measurements are planned | |||
Priority: Necessary | |||
Conditions | |||
Maximum telescope temperature: | 15 K | ||
Minimum telescope temperature: | 5.5 K | ||
Should activity be repeated if focus changes? | No Repeat if focus changes by 0 mm | ||
Maximum absolute pointing uncertainty: | 3600 arcsec (1 sigma radial) | ||
Maximum precision offset uncertainty: | 3600 arcsec (1 sigma radial) | ||
Observatory configuration: | standard | ||
Go/No Go criteria: | Successful completion of MIPS-015 | ||
Duration: 35 minutes
| Real time downlink:
 
No | |
Data Volume (uncompressed): 50 Mbits | |||
List Blocks, AORs, SERs, IERs, or unique sequences required (uplink): Power-on blocks, thermal anneal and Vrst IERs | |||
List Analysis tools required (downlink): Analysis tool for determining optimum Vrst values and a spreadsheet for looking at the thermal diagnostic data | |||
Estimate of data turn around: 24 hours | |||
Description: An automated tool will be developed for processing Vrst optimization data. We will run this tool on the data, and then we will determine whether new Vrst values are needed during the next power-up. | |||
Can proceed in parallel with other activity: No | |||
Must outcome be confirmed before next activity: No | |||
Method of Confirmation: Visual inspection of the data and of the temperature telemetry | |||
Success criteria: The Vrst test will be successful if we collect the appropriate amount of data, if the Ge array biases were turned on and off as expected, and if the stims turned on and off as expected. | |||
Contingency plan: If the Vrst optimization does not run properly, the commanding should be rechecked and corrected. If the anneal heaters fail to operate, we will need to switch to using bias boost or photon flood anneals. | |||
Comments | |||
References: | |||
Additional Comments:
| |||
This activity last updated: 7/2/2002 3:06:27 PM |