| CAID: MIPS-990 | Title: Shut-down Activities, Si only | |
| System: MIPS | Principal: dmkelly | Deputy: cengelbracht |
| Objective: | Perform a standard set of MIPS tasks before
turning off
the instrument. |
| Description: | 1) Take a short exposure 2) Perform thermal anneals on the 24um array 3) Pause 2m to allow the array to settle 3) Take a short exposure 4) Transition from MIPS_OBSERVE to OFF 5) Turn off power to the combined electronics |
| Day: 6.00277777778683 | Suggested Order: | ||
| Must be preceded by these activities (list by CAID): MIPS-900 | |||
| Place in Schedule: At the end of each IOC campaign in which Si but not Ge measurements are planned | |||
| Priority: Necessary | |||
Conditions | |||
| Maximum telescope temperature: | 300 K | ||
| Minimum telescope temperature: | 5.5 K | ||
| Should activity be repeated if focus changes? | No Repeat if focus changes by 0 mm | ||
| Maximum absolute pointing uncertainty: | 3600 arcsec (1 sigma radial) | ||
| Maximum precision offset uncertainty: | 3600 arcsec (1 sigma radial) | ||
| Observatory configuration: | standard | ||
| Go/No Go criteria: | Succesful completion of MIPS-015 | ||
Duration: 12 minutes
| | Real time downlink:
 
No | | |||
| Data Volume (uncompressed): 17 Mbits | |||
| List Blocks, AORs, SERs, IERs, or unique sequences required (uplink): Power-off blocks, 24um thermal anneal IER | |||
| List Analysis tools required (downlink): A spreadsheet for looking at the thermal diagnostic data | |||
| Estimate of data turn around: 24 hours | |||
| Description: The thermal anneal temperatures will be plotted and examined | |||
| Can proceed in parallel with other activity: No | |||
| Must outcome be confirmed before next activity: No | |||
| Method of Confirmation: Visual inspection of the data and of the temperature telemetry | |||
| Success criteria: The thermal anneals will be considered successful if the anneal heaters turn on and off as expected and if the array temperatures change as expected based on ground-based testing. | |||
| Contingency plan: If the anneal heater fails to operate, we will need to switch to using bias boost or photon flood anneals. | |||
Comments | |||
| References: | |||
|
Additional Comments:
To be scheduled before the end of every campaign. | |||
| This activity last updated: 7/2/2002 2:52:59 PM | |||