Sequencer Site SIRTF IOC Activity c. 2002

CAID: MIPS-992 Title: Shut-down Activities, Ge (& Si)
 
System: MIPS Principal: dmkelly Deputy: cengelbracht
Objective:  
Perform a standard set of MIPS tasks before
turning off
            the instrument.
 
Description:
1) Take a short exposure
   2) Perform thermal anneals on all three 
arrays
   3) Perform a Vrst Optimization on the 70um 
and
160um arrays
   4) Transition from MIPS_OBSERVE to OFF
   5) Turn off power to the combined 
electronics
 
Day:   42.4812500000044 Suggested Order:  
 
Must be preceded by these activities (list by CAID):   MIPS-905
 
Place in Schedule:   At the end of each IOC campaign in which Ge measurements are planned
 
Priority:   Necessary


Conditions

Maximum telescope temperature: 15 K
 
Minimum telescope temperature: 5.5 K
 
Should activity be repeated if focus changes?   No     Repeat if focus changes by 0 mm
 
Maximum absolute pointing uncertainty: 3600 arcsec (1 sigma radial)
 
Maximum precision offset uncertainty: 3600 arcsec  (1 sigma radial)
 
Observatory configuration: standard
 
Go/No Go criteria: Successful completion of MIPS-015


Resources

Duration:   19 minutes
 
Real time downlink:   No   

Data Volume (uncompressed): 60 Mbits
 
List Blocks, AORs, SERs, IERs, or unique sequences required (uplink): Power-off blocks, thermal anneal and Vrst IERs
 
List Analysis tools required (downlink):   Analysis tool for determining optimum Vrst values and a spreadsheet for looking at the thermal diagnostic data

Outcome


Estimate of data turn around:   24 hours
 
Description: An automated tool will be developed for processing Vrst optimization data. We will run this tool on the data, and then we will determine whether new Vrst values are needed during the next power-up.
 
Can proceed in parallel with other activity: No
 
Must outcome be confirmed before next activity: No
 
Method of Confirmation:   Visual inspection of the data and of the temperature telemetry
 
 
Success criteria: The Vrst test will be successful if we collect the appropriate amount of data, if the Ge array biases were turned on and off as expected, and if the stims turned on and off as expected. T
 
Contingency plan:  If the Vrst optimization does not run properly, the commanding should be rechecked and corrected. If the anneal heaters fail to operate, we will need to switch to using bias boost or photon flood anneals.
 
 

Comments

 
References:  
 
Additional Comments:
 